Private-Public Partnership for Development was
the theme at the Annual Sessions of the Sri Lanka Economic
Association (SLEA) held two weeks ago at the BMICH. Has this
partnership worked in the crucial area of infrastructure/public
utilities that is the key to growth and development? Although
Sri Lanka liberalized its economy and has unleashed the market
forces to play a greater role in resource allocation, the
development of infrastructure/public utilities has not matched
the rapid increasing demands of the open economy. For instance,
the importation of vehicles has increased rapidly but the roads
have not expanded to accommodate this increase resulting in
major traffic congestions.
Sri Lanka on average has been spending 3.5 per
cent of GDP on infrastructure development. However, in some
years it has been very low because the capital expenditure of
the government is always the victim in a budget balancing
exercise and the cuts it has suffered during the last two
decades has been significant and thus seriously affected the
on-going infrastructure development activities. In countries
such as Malaysia and Thailand, 6-8 per cent of GDP is allocated
for infrastructure development. Due to massive budgetary
problems at the time of the North/East war, the government
decided that the private sector should be invited to play a role
in infrastructure/public utilities development. The
infrastructure/public utilities earmarked for private sector
participation were ports, telecommunications, power, roads,
railways, water, etc.
Required Policy Framework
In the 1980s various approaches for private
sector participation in infrastructure emerged in the world.
They ranged from service contract (concession, lease, franchise)
to Build Operate Transfer (BOT) to Build Operate Own (BOO) type
arrangements. The World Development Report of 1994 gives a good
description of these techniques. The International Financial
Institutions argued that private sector participation in
infrastructure could lead to delivering less expensive and
reliable services to the people at large. However, in order to
realize these benefits the government had to create a conducive
legal and regulatory framework (contract, property rights,
competition, and so on), and ease risk perceptions that hinder
investment. It was also argued that BOO/BOT is an innovative
approach compared to sovereign borrowing and debt financing — it
induced financial ‘additionality’, technology transfer, and
skill development that offset any disadvantages the technique
possessed.
Accordingly, in the early 1990s, the Secretariat
for Infrastructure Development (SIDI) and the Private Sector
Infrastructure Development Corporation (PSIDC) (with adequate
funds for private investors to borrow) were established in Sri
Lanka. In the mid-1990s the SIDI was absorbed by the BOI and
renamed Bureau of Infrastructure Investment (BII) with
additional powers. Sri Lankan public utilities have been
traditionally overstaffed and functioned as dispensers of
subsidized services. Thus, the political risks were on the high
side and there was a case for considering modalities of
introducing private partnerships that involved less political
risks. At least as an interim step before adopting of BOT which
required a change in the status quo, was the creation of a new
regulatory framework. But Sri Lanka embarked on ambitious BOT
projects in the power and roads sectors before getting the legal
and regulatory framework in place.
Progress and Problems
If we take stock of the progress in
infrastructure/public utilities development over the last 10-12
years, with private sector involvement, it is far from
satisfactory. Of course there are some success stories such as
the telecommunications, Colombo Port, and the Sri Lankan
Airlines but these were not BOO/BOT arrangements and involved
developing a public-private partnership via divestiture of
shares below 50 per cent to the private sector. But if we
examine the BOO/BOT type of projects the record is
unsatisfactory.
A number of problems can be identified. First,
the fundamentals governing the basic legal framework for
inviting the private sector for infrastructure development was
not in place. There has not been political and economic
stability for large scale private investment to take place. In
such an environment, the question of political commitment to go
ahead with a project under different political regimes has
remained a question. Second, the institutional and regulatory
framework to govern the public-private partnership has been far
from satisfactory; and the risk minimizing strategy has been
inadequate. It appears that these areas have been gradually
evolving with ups and downs with the changes in political
regimes.
In regard to the first, the best example is the
Trincomalee coal power plant project that was negotiated before
the change of government in 1994. The earlier government gave
the winning bidder – Mihaly International Canada – a one year
period of exclusivity to prepare a comprehensive feasibility
study. This was done by issuing a Letter of Intent to the
company. However, the new government that assumed office decided
to terminate this exclusivity indicating that they had failed to
meet the conditions of the contract. Although the LOI did not
constitute a legal obligation on the part of the government to
enter into an implementation agreement, the lack of a formal
legal agreement to back the documentation procedure led to a
dispute between the government and Mihaly, with the company
threatening to claim US $ 150 million as damages and
compensation. A more recent example is the row over the fuel
subsidy claim from the Treasury by the Lanka Indian Oil
Corporation (LIOC) where the privatization agreement under the
previous government is subject to different interpretation by
the LIOC and the Treasury.
The institutional structure to promote a
private-public partnership had many shortcomings and they were
not fully addressed by the BII either. First, the decision
making process was plagued by political interference because the
structure was not streamlined. Second, the coordinating network
with other agencies such as the Urban Development Authority,
Road Development Authority, line Ministries, Labour Department,
etc., was not effective; and third, the institutions did not
have the statutory authority to take decisions on tariff or
pricing policy and left such decisions to be made by
sub-committees appointed by the Cabinet. Consequent to these
shortcomings, projects have been manipulated by various
technical and non-technical committees and as a result some
projects got delayed or halted.
Designing a suitable regulatory framework has
also been a problem. Designing a workable regulatory framework
requires considerable skills and expertise given the realities
of regulatory failures ranging from regulatory capture to lack
of constant regulatory innovation with increasing competition.
Besides, regulation can sometimes distort competition by its
impact on incentives, varies according to the public utility,
and costly to set up and often fail to achieve the goals.
Regulatory bodies such as the Sri Lanka Telecom Regulatory
Authority, National Transport Commission, etc., were subject to
political interference and could not function as workable
independent regulatory bodies. The electricity sector still does
not have a proper regulatory body. During the mid-1990s even
designing workable power purchase agreements and risk allocation
between the public and private sector were not satisfactory in
the power sector. Consequently, establishment of most thermal
power generation plants got delayed. The fate of the Colombo-Katunayake
highway is another good example of messing up of the contract
with the private partner.
Hong Kong based mega investor Gordon Wu said in
1996 that "Sri Lanka spends more time negotiating a deal than
building the projects." This statement basically summarized the
fate of most private-public partnerships in the area of
infrastructure under BOT arrangements. This situation had not
changed much over the years, so much so, the Secretary to the
Treasury in his inaugural address to the SLEA Annual Sessions
echoed such sentiments by stating that several projects that
should have taken place some time ago are being implemented
today and the government is spending more time on
conceptualizing rather than realization of the dreams foreseen
for the future (Daily Mirror, 18 July 2005).
Recognizing the need to get the act together and
move forward in BOO/BOT projects an initiative was taken to
create a good regulatory and legal framework that has a workable
independence. Accordingly, a Public Utility Commission was
established in 2002, which was basically a multi-sector
regulatory authority – where all regulatory bodies for public
utilities/infrastructure would be housed. The objective was to
exploit the economies of scope in the regulatory process related
to the degree of commonality in the objective (rights of way)
and form (price cap) of regulation and was based on the
assumption that public hearings, cost of studies, etc., are
substitutable across sectors. It was supposed to be a
skills-based institution with economists, lawyers, engineers and
project teams incorporated into it.
Since the change of government in 2004, the
Strategic Enterprise Management Agency (SEMA) has taken over the
restructuring of public utilities/infrastructure. It seems to be
toying with the idea of introducing the Temasek model of
Singapore for restructuring some of the public utilities – run
on a competitive and commercial basis without state interference
or favours under state ownership. However, the plans of SEMA are
not yet clear since private companies like Bharat Petroleum have
been entertained on an ad hoc basis for restructuring a public
utility such as the Petroleum Corporation. Furthermore, SEMA’s
relationship with the Public Utilities Commission is far from
clear.
But what is clear is the following – the problem
in Sri Lanka is not the lack of private finances for
infrastructure projects but managing the transition for private
sector involvement. Sri Lanka has not been very successful in
minimizing the teething problems in the transition and the
required institutional, legal, and regulatory structures seem to
be still evolving. If proper private-public partnership is to be
introduced to infrastructure/public utilities, the government
should engage in an open dialogue with the stake holders and
civil society. It is only then that the teething problems could
be resolved and implementation could be expedited with least
political resistance.